Clean energy journalism for a cooler tomorrow

US clean energy rollout continues to be hamstrung by grid challenges

Recent efforts at permitting reform have done little to address the well-known issues of inadequate transmission and jam-packed interconnection queues.
By Akielly Hu

  • Link copied to clipboard
A transmission power line and several wind turbines are seen in stark silhouette against the backdrop of a sunset
(Iamadventure/Shutterstock.com)

This story was first published by Grist.

Clean power installations declined in 2022 for the first time in five years, according to a report published by the American Clean Power Association last month. The group found that permitting issues, including delays in connecting projects to the grid and a shortage of transmission lines, played a major role in the slowdown.

In total, more than 25.5 gigawatts of clean power were installed last year — enough to power millions of average U.S. homes. That represents a drop of 15 percent from 2021 deployment levels. The report defines clean power as onshore and offshore wind, utility-scale solar and battery storage technology. American Clean Power warns that if the country continues at a rate of 25.5 gigawatts annually, the U.S. will install only 30 percent of the clean power needed to reach President Biden’s goal of decarbonizing the power sector by 2035.

It’s a stark reminder of how permitting — the various approval processes needed for projects to get sited and connected to the grid — may make or break the buildout of clean energy. Experts have long said that permitting changes will be needed to decarbonize the power sector, and American Clean Power’s findings arrived just a week before lawmakers finally reached a deal on permitting reform to raise the debt ceiling. But some in the field say the compromise reached in the debt ceiling deal won’t address the two biggest challenges to permitting renewables: delays in connecting projects to the electrical grid and a shortage of transmission lines to move power.

It is critical that Congress build upon these initial steps,” said Jason Grumet, CEO of the American Clean Power Association, in a statement on the recent debt ceiling deal. Absent significant improvements in the siting and construction of new clean power transmission capabilities, our nation will fail to achieve critical economic, national security and climate goals.”

This congressional session, both Republicans looking to streamline permitting for fossil fuels and Democratic lawmakers hoping to ramp up renewable power introduced bills to update the decades-old system. Permitting reform in the debt limit bill, which Biden signed in early June, primarily involves amendments to the National Environmental Policy Act, or NEPA. The foundational law from 1969 requires the government to assess the potential environmental impacts of any major infrastructure projects before breaking ground. The debt ceiling law speeds up this review process, setting a one-year deadline for most assessments and a two-year deadline for stricter impact studies. It also requires that one federal agency take the lead in conducting these reviews and sets new page limits for the studies to minimize paperwork, among other revisions with impacts that are still up for debate.

Energy advocates argue that these NEPA amendments weaken the law’s public input processes, limiting the ability of frontline communities to weigh in on fossil fuel and other major projects that exacerbate pollution burdens.

The last thing we should consider is gutting environmental rules,” Sachu Constantine, executive director of the solar advocacy group Vote Solar, told Grist.

Speeding up interconnection is a must

A more pressing issue, Constantine and other experts say, is interconnection, or the process of hooking up projects to the grid. Developers looking to connect a project to the grid first apply with their regional grid operator to join what’s called an interconnection queue.” After a project enters the queue, the grid operator proceeds to conduct a series of studies to determine if new grid infrastructure or upgrades will be needed to connect the new project. It then assigns the costs of those upgrades to the project.

The lengthy process is producing a huge backlog of projects waiting to be connected. As of December 2022, more than 2,000 gigawatts of electricity generation and storage projects were waiting to connect with the electric grid. That’s up from 1,400 GW at the end of 2021, according to a recent report by Lawrence Berkeley National Laboratory. Ninety-five percent of projects left hanging are clean energy and battery storage projects, the latter of which can capture excess renewable energy and deploy it to the grid when the wind isn’t blowing and the sun isn’t shining.

Joe Rand, lead author of the Lawrence Berkeley National Laboratory report, says the growing backlog is the result of a two-decade-old system that’s yet to catch up with a rapidly shifting energy mix. The current process was not designed for a rapid energy transition like we’re trying to meet right now,” Rand told Grist. The interconnection system was originally designed to process a few centralized fossil fuel power plants rather than thousands of smaller renewable projects springing up all around the country.

The Berkeley Lab report also found that only 21 percent of projects in the interconnection queue between 2000 and 2017 ultimately came online. That’s in part due to the lengthy delays, but also due to the growing costs for upgrades required to connect to the grid. The lab found that average interconnection costs have grown substantially over time” and are higher for wind, storage and solar than for natural gas. The main driver of costs is the increasingly frequent need for broader network upgrades” — meaning that projects must sometimes pay for upgrades to the network, in some cases for infrastructure that’s located hundreds of miles away from the project site.

Last year, the Federal Energy Regulatory Commission, or FERC, the agency regulating electricity and natural gas transmission, proposed a new rule to accelerate projects through the congested interconnection queue.

But some experts worry that FERC’s proposal fails to address the problem of staffing shortages. Interconnection studies rely on a workforce of engineers at grid operators, and experts say there are not enough to get the job done, a labor problem without immediate policy solutions. As Rand puts it, the workforce is a fundamental constraint. They can only do so many studies in a given year.”

And even if grid operators manage to connect every backlogged project to the grid, another issue looms: There aren’t enough high-voltage transmission lines to move all that new power to consumers.

In a report last year, the National Renewable Energy Laboratory projected that in order for the U.S. to achieve 100 percent clean electricity by 2035, interregional transmission — power lines that cut across state lines — will need to double or triple in capacity. And researchers at Princeton University have warned that if the rate of transmission construction does not double that of the last decade, 80 percent of potential emissions reductions delivered by the 2022 Inflation Reduction Act by 2030 will be lost.

Yet the U.S. is actually trending downward when it comes to transmission builds. The American Clean Power Association found that new transmission builds in 2022 dropped 50 percent from 2021 levels. Utilities and transmission developers added only 675 miles of new transmission last year — the smallest number of miles built in the last decade.

In response, Rand, Constantine and others call for increased, proactive transmission building. But so far, there’s been little movement by federal policymakers to speed up transmission buildout — including interregional transmission crucial for moving solar and wind power produced in rural areas to urban centers. The debt ceiling law requires grid authorities to complete a study on interregional transmission capacity within 18 months, but it does not mandate or otherwise enable new transmission deployments.

Despite the challenges, Rand remains optimistic that policymakers will rise up to the challenge of a growing renewables sector. By the end of 2022, 137 gigawatts of new clean power were either under construction or in advanced development — 14 percent above 2021 levels, in part due to new clean energy incentives available under the Inflation Reduction Act.

We’re just seeing all this interest in wind, solar and storage, very little in gas, and no coal,” Rand said. It’s clear to me that our electric sector is poised to move rapidly in the right direction.”

Akielly Hu is a freelance climate reporter and a former news and politics fellow at Grist.